Overhill Farm

Scotland

Battery Energy Storage System (BESS) project sold in the United Kingdom

Project

The Overhill project is a Battery Energy Storage System (BESS) development located in Rothiernorman, Scotland. This project is part of a joint venture between One Planet Developments Limited, Viridi RE, and Green Enesys Group. Spanning approximately 3.6 hectares (9 acres), the project is strategically situated adjacent to the new 33kV Rothienorman substation. The planning application for the project was submitted on October 21, 2022, with a determination by March 1, 2023. The Overhill BESS project is scheduled to come online in the fourth quarter of 2024. This project represents the first successful exit for the joint venture, which is developing a pipeline of over 1GW of UK BESS and solar projects and has been successfully sold to Pulse Clean Energy.

Highlights

The Overhill project features a total capacity of 50 MW, covering a 3.6-hectare site. The project has a 40-year lease period. Key advantages of the project include enhanced grid stability, improved energy efficiency, and the ability to store and supply energy during peak demand periods.

50
MW
100
MWh
Development Process

Throughout the entire development process, close collaboration with local authorities and stakeholders was maintained to ensure the project's successful completion. 

Planning Application

Submitted on October 21, 2022, with a planning determination by March 1, 2023.

Strategic Location

The site is adjacent to the new 400/132/33kV Rothienorman substation, optimizing connectivity and efficiency.

Collaborative Development

The project is part of a joint venture between One Planet Developments Limited, Viridi RE, and Green Enesys Group, leveraging extensive experience in solar and BESS projects.

Technical Planning

Detailed planning to ensure seamless integration with the existing electrical network, with a connection voltage of 33kV.

Future-Proofing

The project is designed to meet future energy storage needs, supporting the broader 1GW+ pipeline of BESS and solar projects being developed by the joint venture.